MIL-STD-1330D(SH)
20 September 1996
oil, and should also protect the material from temperature extremes of below 40EF and above 100EF. The certification sticker or tag shall be attached so as to be visible for inspection.
5.16.3.2 Inspection of packaging. Prior to use or transport, the packaging of all certified oxygen clean materials shall be inspected. If the outer package is torn or damaged, but the inside package is intact, replace the outer package. If the inside package is torn or damaged exposing the oxygen cleaned surface to the ambient atmosphere, the item shall be recleaned and recertified as specified herein. An exception is high valued items such as valves, regulators, and
compressors of which local engineering approval to use 5.12 shall be obtained (see
6.3). For shipboard storage, the packaging of all certified oxygen clean material
should be inspected every 3 years to ensure ready spares are available.
5.17 In-process inspections.
5.17.1 Inspection. When required by table XII, an inspector or witness shall observe the applicable operation for compliance with this standard. The witness or inspectors shall be designated by the local activity.
TABLE XII. In-process operation inspections.
Procedure |
Operation |
Operation performed by |
Inspector or witness |
5.1.2 |
Facility maintenance |
Not applicable |
Not required |
5.2 and 5.16 |
Cleaning and packaging of components in a cleanroom |
Not applicable |
Not required |
5.2 and 5.16 |
Cleaning and packaging of components in a controlled area |
Not applicable |
Required 1/ |
5.3 |
Cleaning of flasks |
Not applicable |
Not required |
5.3 |
Inspection of flasks |
Not applicable |
Required 1/ |
5.4 |
Instrument cleaning |
Not applicable |
Not required |
5.5 through 5.8 |
Cleaning of piping systems |
Not applicable |
Not required |
5.9.1 and 5.9.2 |
Pressure and operational testing |
Not applicable |
Not required |
5.9.3 |
Gas analysis |
A facility which is recognized and accepted by NAVSEA |
Not required |
5.10 |
Maintenance of cleanliness |
Not applicable |
Required 1/ 2/ |
5.11 |
Piping repairs between flasks |
Not applicable |
Not required |
See footnotes at end of table.