MIL-DTL-1213F
4.4 Lot records. Manufacturers shall keep lot records for 3 years minimum. Manufacturers shall
monitor for compliance to the prescribed procedures, and observe that satisfactory manufacturing
conditions and records on lots are maintained for these hose assemblies. The records, including as a
minimum, an attributes summary of all quality conformance inspections conducted on each lot, shall be
available to review by government at all times.
4.5 First article inspection. First article inspection may be performed at a laboratory acceptable to the
procuring activity.
4.5.1 Samples for first article. Samples for first article inspection shall be representative of the
products proposed to be furnished to this specification, see table IV.
4.5.2 First article inspection routine. All samples shall be subjected to first article testing in
accordance with table I.
4.5.3 Failures. All samples must meet all of the contract requirements. Failure of a sample unit to
pass any test shall be cause for rejection of the entire lot and to grant first article approval, see 4.5.
4.5.4 Disposition of samples. First article samples shall be furnished to the Government as directed
by the contracting officer (see 6.2).
TABLE I. First article inspection.
Inspection
Requirement
Test method
Visual
Dimensional
Functioning test
Destructive test
4.6 Conformance inspection. Conformance inspection shall be done at the time of an order. The
TABLE II. Conformance
Inspection
Requirement
Test method
Visual
Dimensional
5